Rebuilding of COB#4 (Package-1, Battery Proper)
| # | Description | Estimate Price | Bid Prices |
|---|---|---|---|
| 1 | Design & Engineering | 25.7200 |
BEC & Consortium
39.9300
MECON Limited
29.5300
|
| 2 | Supply of Plant & Equipment Incl. Technological Structures | 274.3800 |
BEC & Consortium
336.1500
MECON Limited
419.1600
|
| 3 | Supply of Building steel structures including sheeting and glazing | 41.0900 |
BEC & Consortium
3.7800
MECON Limited
-
|
| 4 | Supply of Refractories | 90.1900 |
BEC & Consortium
129.8000
MECON Limited
107.1600
|
| 5 | Civil Engineering Work including all related supplies- for equipment foundation | 46.5100 |
BEC & Consortium
70.8000
MECON Limited
90.5600
|
| 6 | Civil Engineering Work including all related supplies- Others | 14.0100 |
BEC & Consortium
23.6000
MECON Limited
5.3100
|
| 7 | Storage, Handling, Erection (including dismantling ) of Plant & Equipments & Refractories including Commisioning and PG tests of the facilities | 60.6900 |
BEC & Consortium
94.4000
MECON Limited
90.6500
|
| 8 | Storage, Handling and Erection of Building Steel Structures | 7.5400 |
BEC & Consortium
2.3600
MECON Limited
-
|
| 9 | Foreign Supervision charges in India during erection, startup, commissioning and PG test for ____mandays | - |
BEC & Consortium
12.6500
MECON Limited
-
|
| 10 | Training charges: (a) For ___________ Foreign mandays, (b) For ___________Indian mandays | - |
BEC & Consortium
-
MECON Limited
0.1200
|
| 11 | Customs, Port clearance (excluding duties & cess to be paid by Employer) and Inland transportation (for all items quoted in foreign currency) | - |
BEC & Consortium
-
MECON Limited
-
|
| 12 | Comprehensive Marine / transit & Storage-cum-erection insurance | - |
BEC & Consortium
0.3500
MECON Limited
2.5700
|
| 13 | Supply of 2 years O & M spares | - |
BEC & Consortium
-
MECON Limited
-
|