Installation of Coke Oven Battery # 7 at RSP
| # | Description | Estimate Price | Bid Prices |
|---|---|---|---|
| 1 | Design & Engineering | 47.5000 |
L&T and Consortium
40.7300
|
| 2 | Supply of Plant & Equipment Incl. Technological Structures | 608.1400 |
L&T and Consortium
531.4000
|
| 3 | Supply of Building steel structures including sheeting and glazing | 11.2100 |
L&T and Consortium
55.1200
|
| 4 | Supply of Refractories | 26.9000 |
L&T and Consortium
22.5500
|
| 5 | Civil Engineering Work including all related supplies- for equipment foundation | 47.3100 |
L&T and Consortium
60.4200
|
| 6 | Civil Engineering Work including all related supplies- Others | 21.6100 |
L&T and Consortium
36.5500
|
| 7 | Storage, Handling, Erection (including dismantling ) of Plant & Equipments & Refractories including Commisioning and PG tests of the facilities | 100.6900 |
L&T and Consortium
117.3000
|
| 8 | Storage, Handling and Erection of Building Steel Structures | 2.3600 |
L&T and Consortium
21.7000
|
| 9 | Foreign Supervision charges in India during erection, startup, commissioning and PG test | 15.8400 |
L&T and Consortium
4.5300
|
| 10 | Training charges (a) For Foreign mandays, (b) For Indian mandays | 0.6300 |
L&T and Consortium
0.8500
|
| 11 | Customs, Port clearance (excluding duties & cess to be paid by Employer) and Inland transportation (for all items quoted in foreign currency) | - |
L&T and Consortium
-
|
| 12 | Comprehensive Marine / transit & Storage-cum-erection insurance | 0.7200 |
L&T and Consortium
5.0800
|
| 13 | Supply of 2 years O & M spares | - |
L&T and Consortium
-
|