Rebuilding of Coke Oven Battery No.-7 (Battery Proper-Package No. 1)
| # | Description | Estimate Price | Bid Prices |
|---|---|---|---|
| 1 | Design & Engineering | 11.2400 |
BEC Ltd. & Consortium
18.8100
Gillander Arbuthnot & Co Ltd. & Consortium
6.7100
L & T Ltd. and Consortium
10.5600
MECON Ltd.
6.8400
|
| 2 | Supply of Plant & Eqpt. Incl. Technological Strs | 71.9100 |
BEC Ltd. & Consortium
88.4500
Gillander Arbuthnot & Co Ltd. & Consortium
104.5600
L & T Ltd. and Consortium
91.2400
MECON Ltd.
97.3600
|
| 3 | Supply of Building steel structures including Sheeting and Glazing | 5.0400 |
BEC Ltd. & Consortium
-
Gillander Arbuthnot & Co Ltd. & Consortium
-
L & T Ltd. and Consortium
10.0800
MECON Ltd.
-
|
| 4 | Supply of Refractories | 1.7300 |
BEC Ltd. & Consortium
1.1500
Gillander Arbuthnot & Co Ltd. & Consortium
5.4800
L & T Ltd. and Consortium
1.2300
MECON Ltd.
-
|
| 5 | Civil Engg. Work including all related supplies | 6.8800 |
BEC Ltd. & Consortium
5.6200
Gillander Arbuthnot & Co Ltd. & Consortium
10.9300
L & T Ltd. and Consortium
34.0000
MECON Ltd.
6.1600
|
| 6 | Storage, handling, erection of plant & Equipment , Building Steel Structures & Refractories including Commissioning and PG Tests of the Facilities | 30.7400 |
BEC Ltd. & Consortium
16.8500
Gillander Arbuthnot & Co Ltd. & Consortium
26.2200
L & T Ltd. and Consortium
40.0900
MECON Ltd.
22.2900
|
| 7 | Foreign supervision charges in India during erection, startup, commissioning & PG test for ________ mandays | - |
BEC Ltd. & Consortium
4.7700
Gillander Arbuthnot & Co Ltd. & Consortium
4.4300
L & T Ltd. and Consortium
1.8500
MECON Ltd.
-
|
| 8 | Foreign training charges for _________ mandays | - |
BEC Ltd. & Consortium
-
Gillander Arbuthnot & Co Ltd. & Consortium
-
L & T Ltd. and Consortium
-
MECON Ltd.
-
|
| 9 | For all items quoted in Foreign Currency | - |
BEC Ltd. & Consortium
-
Gillander Arbuthnot & Co Ltd. & Consortium
-
L & T Ltd. and Consortium
-
MECON Ltd.
-
|
| 10 | a) Ocean Freight | - |
BEC Ltd. & Consortium
-
Gillander Arbuthnot & Co Ltd. & Consortium
1.1600
L & T Ltd. and Consortium
-
MECON Ltd.
-
|
| 11 | b) Customs, Port clearance (Excluding duties & cess to be paid by Employer) and inland transportation | - |
BEC Ltd. & Consortium
-
Gillander Arbuthnot & Co Ltd. & Consortium
0.8400
L & T Ltd. and Consortium
2.4700
MECON Ltd.
-
|
| 12 | a) Comprehensive/ Transit, Storage cum erection insurance | - |
BEC Ltd. & Consortium
0.2000
Gillander Arbuthnot & Co Ltd. & Consortium
0.9000
L & T Ltd. and Consortium
-
MECON Ltd.
-
|
| 13 | b) Marine insurance for all items quoted in Foreign Currency | - |
BEC Ltd. & Consortium
-
Gillander Arbuthnot & Co Ltd. & Consortium
0.0900
L & T Ltd. and Consortium
-
MECON Ltd.
-
|