Replacement of secondary Gyratory Crusher into Cone Crusher at Ore Handling Plant of Barsua Iron Mines

Ref: CET-17(4)/4916-17 Plant: ROURKELA STEEL PLANT Date: 04 Feb 2025 File: m_4916-PBE.xlsx
# Description Estimate Price Bid Prices
1 Design & Engineering 0.9000
Larsen & Toubro Limited 0.2000
Sandvik Mining And Rock Technology India Private Limited 0.3300
2 Supply of Plant & Equipment Incl. Technological Structures 13.7900
Larsen & Toubro Limited 13.8800
Sandvik Mining And Rock Technology India Private Limited 30.6600
3 Supply of Building steel structures including Sheeting and Glazing -
Larsen & Toubro Limited 0.1300
Sandvik Mining And Rock Technology India Private Limited 0.5200
4 Supply of Refractories -
Larsen & Toubro Limited -
Sandvik Mining And Rock Technology India Private Limited -
5 Civil Engineering Work including all related supplies- for equipment foundation 0.0200
Larsen & Toubro Limited 0.0900
Sandvik Mining And Rock Technology India Private Limited 0.4100
6 Civil Engineering Work including all related supplies- Others 1.4200
Larsen & Toubro Limited 0.3300
Sandvik Mining And Rock Technology India Private Limited 1.5600
7 Storage, Handling, Erection of Plant & Equipments & Refractories including Commisioning and PG tests of the facilities 3.0700
Larsen & Toubro Limited 2.7300
Sandvik Mining And Rock Technology India Private Limited 1.6500
8 Storage, Handling and Erection of Building Steel Structures -
Larsen & Toubro Limited 0.4200
Sandvik Mining And Rock Technology India Private Limited 0.0900
9 Foreign Supervision charges in India during erection, startup, commissioning and PG test for _____mandays -
Larsen & Toubro Limited -
Sandvik Mining And Rock Technology India Private Limited -
10 Training charges: (a) For ___________ Foreign mandays, (b) For ___________Indian mandays -
Larsen & Toubro Limited 0.0400
Sandvik Mining And Rock Technology India Private Limited 0.0600
11 Customs, Port clearance (excluding duties & cess to be paid by Employer) and Inland transportation (for all items quoted in foreign currency) -
Larsen & Toubro Limited -
Sandvik Mining And Rock Technology India Private Limited -
12 Comprehensive / Transit Storage-cum-erection insurance -
Larsen & Toubro Limited 0.0500
Sandvik Mining And Rock Technology India Private Limited 0.2900
13 Supply of 2 years O & M spares 0.4100
Larsen & Toubro Limited 1.7700
Sandvik Mining And Rock Technology India Private Limited 6.7600