Replacement of secondary Gyratory Crusher into Cone Crusher at Ore Handling Plant of Barsua Iron Mines
| # | Description | Estimate Price | Bid Prices |
|---|---|---|---|
| 1 | Design & Engineering | 0.9000 |
Larsen & Toubro Limited
0.2000
Sandvik Mining And Rock Technology India Private Limited
0.3300
|
| 2 | Supply of Plant & Equipment Incl. Technological Structures | 13.7900 |
Larsen & Toubro Limited
13.8800
Sandvik Mining And Rock Technology India Private Limited
30.6600
|
| 3 | Supply of Building steel structures including Sheeting and Glazing | - |
Larsen & Toubro Limited
0.1300
Sandvik Mining And Rock Technology India Private Limited
0.5200
|
| 4 | Supply of Refractories | - |
Larsen & Toubro Limited
-
Sandvik Mining And Rock Technology India Private Limited
-
|
| 5 | Civil Engineering Work including all related supplies- for equipment foundation | 0.0200 |
Larsen & Toubro Limited
0.0900
Sandvik Mining And Rock Technology India Private Limited
0.4100
|
| 6 | Civil Engineering Work including all related supplies- Others | 1.4200 |
Larsen & Toubro Limited
0.3300
Sandvik Mining And Rock Technology India Private Limited
1.5600
|
| 7 | Storage, Handling, Erection of Plant & Equipments & Refractories including Commisioning and PG tests of the facilities | 3.0700 |
Larsen & Toubro Limited
2.7300
Sandvik Mining And Rock Technology India Private Limited
1.6500
|
| 8 | Storage, Handling and Erection of Building Steel Structures | - |
Larsen & Toubro Limited
0.4200
Sandvik Mining And Rock Technology India Private Limited
0.0900
|
| 9 | Foreign Supervision charges in India during erection, startup, commissioning and PG test for _____mandays | - |
Larsen & Toubro Limited
-
Sandvik Mining And Rock Technology India Private Limited
-
|
| 10 | Training charges: (a) For ___________ Foreign mandays, (b) For ___________Indian mandays | - |
Larsen & Toubro Limited
0.0400
Sandvik Mining And Rock Technology India Private Limited
0.0600
|
| 11 | Customs, Port clearance (excluding duties & cess to be paid by Employer) and Inland transportation (for all items quoted in foreign currency) | - |
Larsen & Toubro Limited
-
Sandvik Mining And Rock Technology India Private Limited
-
|
| 12 | Comprehensive / Transit Storage-cum-erection insurance | - |
Larsen & Toubro Limited
0.0500
Sandvik Mining And Rock Technology India Private Limited
0.2900
|
| 13 | Supply of 2 years O & M spares | 0.4100 |
Larsen & Toubro Limited
1.7700
Sandvik Mining And Rock Technology India Private Limited
6.7600
|